Senegal's 2027 Railway Programme Stalls as Parliament Withholds Budget Approval

The railway programme includes CFA16.70 billion for state-executed investment alongside CFA26.53 billion in current transfers. The distinction is material for contractors and suppliers assessing the proposed railway spending rather than treating the full programme figure as funding for new works. The government's 2027 priorities include rehabilitation of the existing Dakar–Tambacounda railway, while its separate standard-gauge proposal remains part of a longer-term network plan. The committee decision also means the proposed ministry


  • Senegal's draft 2027 finance law sets out a proposed railway programme within the Ministry of Land and Air Transport's budget.
  • The draft 2027 railway programme provides CFA44.17 billion in payment appropriations and CFA51.79 billion in commitment authorisations.
  • Railway payment appropriations include CFA26.53 billion in current transfers and CFA16.70 billion in state-executed investments.
  • The draft finance law includes CFA6.70 billion in proposed external-financing payment appropriations for the Dakar–AIBD rail scheme.
  • Senegal identifies Dakar–Tambacounda railway rehabilitation as a 2027 infrastructure priority.
  • The National Assembly reported that the transport ministry's CFA104.34 billion draft budget was not adopted in committee on 13 November 2026.

Senegal's proposed 2027 railway programme contains CFA44.17 billion in payment appropriations, although the transport ministry's wider budget proposal failed to secure adoption by a parliamentary committee on 13 November 2026. The draft finance law sets out a proposed CFA104.34 billion in ministry payment appropriations, covering rail, road, aviation and administration.

The National Assembly said on 14 November that its Finance and Budgetary Control Committee, meeting jointly with the committee responsible for infrastructure and transport, had examined the proposed ministry budget presented by Minister Lahat Ndiaye. Members raised questions about the coherence and transparency of the proposal. The concerns recorded by the Assembly included road conditions, ageing vehicles, traffic accidents, congestion and inadequate road signage. At the end of the committee proceedings, the proposed ministry budget was not adopted.

The decision concerns the proposal's examination in committee. On 18 November, the National Assembly in plenary voted on the first part of the 2027 finance bill, covering revenue, the general budget spending ceiling and borrowing authorisations, and that part was not adopted.

What the Railway Programme Contains

The government's draft finance law lists CFA51.79 billion in commitment authorisations and CFA44.17 billion in payment appropriations for Programme 2028, Development and Modernisation of the Railway Network and Transport Systems. The figures represent the proposed railway programme as a whole rather than an allocation to one line or project.

Of the payment appropriations, CFA26.53 billion is classified as current transfers, CFA16.70 billion as investments executed by the state and CFA850 million as capital transfers. Personnel expenditure accounts for CFA68.13 million and goods and services for CFA21.45 million. This distinction matters when interpreting the programme total: the CFA44.17 billion is not solely a construction budget.

The draft finance law's annex of externally financed projects separately lists CFA6.70 billion in proposed 2027 payment appropriations under the construction of the Dakar–AIBD rail service. Four financing lines are named: CFA2.46 billion from the African Development Bank/African Development Fund, CFA1.12 billion from BADEA, CFA1.12 billion from the West African Development Bank (BOAD), and CFA2.00 billion from Bpifrance. These amounts are identified against the Dakar–AIBD scheme, not the planned Dakar–Tambacounda standard-gauge line.

Two Different Dakar–Tambacounda Railway Programmes

The 2027 draft finance law identifies rehabilitation of the Dakar–Tambacounda railway among the government's priority infrastructure interventions. Its railway policy separates work on the existing metre-gauge route from the proposed standard-gauge network.

At a railway-project meeting on 20 February 2026, the government described rehabilitation and an intermediate phase of safer operation on the metre-gauge Dakar–Tambacounda corridor as priorities. It placed the future standard-gauge Dakar–Tambacounda line, with proposed extensions towards Kidira and Kédougou, in a longer-term network programme alongside the third phase of the regional express train (TER).

The proposed 2027 railway appropriations are thus a programme-level budget proposal. The National Assembly's committee decision and any subsequent changes to the finance bill remain relevant to the status of that spending plan.

Footnote

Written by Phillippa Dean

Related News Articles