AfDB Publishes Environmental and Social Studies for Tunis–Bizerte Rail Rehabilitation

The Tunis–Bizerte line links Greater Tunis with the port city of Bizerte and its industries, and its rehabilitation would restore a safer, faster rail option for passengers and freight such as cement and steel. With the environmental and social documents now public, the AfDB-supported project moves towards design and tendering, which the ESIA runs to the end of the first quarter of 2027.


  • The AfDB has published the environmental and social documents for Phase 1 of the Tunis–Bizerte rail rehabilitation programme.
  • SNCFT plans to rehabilitate Line 1 between Jedeida and Bizerte, about 72km, and a branch of about 6.5km to Menzel Bourguiba.
  • Phase 1 works stay within the existing right of way and include track renewal, drainage, structures, platforms and fencing.
  • Eight road level crossings are to be upgraded as a priority tranche.
  • The ESIA puts the works phase at about 24 months, with design and tender documents due by the end of the first quarter of 2027.
  • The stakeholder engagement plan names the AfDB and the European Investment Bank as lenders.

The African Development Bank (AfDB) has published the environmental and social documents for Phase 1 of a multi-tranche financing programme to rehabilitate the Tunis–Bizerte rail service, which the Société Nationale des Chemins de Fer Tunisiens (SNCFT) plans to implement. According to the AfDB, the Bank has agreed to provide financing, implementation support and project monitoring.

The package, published on 13 November under project code P-TN-DC0-012, comprises an environmental and social management plan to be annexed to the financing agreement, an environmental and social impact assessment (ESIA), SNCFT's environmental and social policy, an assessment of its environmental and social management system and a stakeholder engagement plan. The stakeholder engagement plan names the European Investment Bank (EIB) alongside the AfDB as lenders.

Route and Scope

The ESIA, prepared for SNCFT by Bureau Tunisien des Études, covers Line 1 between Jedeida and Bizerte, a route of about 72km, together with a branch of about 6.5km from Tinja to Menzel Bourguiba. The line passes Chaouat, Sidi Othmen, Aïn Ghlel, Mateur, Tinja and La Pêcherie, and Mateur is a junction with the lines to Tabarka and Béja.

Phase 1 centres on rehabilitating the existing railway infrastructure, with the works kept within the current right of way. They include removing the existing track and renewing the track superstructure, earthworks, platforms, drainage, hydraulic and engineering structures, and permanent fencing, with solid walls in urban areas and anti-intrusion mesh in rural areas.

Eight road level crossings are to be upgraded with new barriers, flashing red lights, audible warnings, road markings, concrete surfacing between the rails and drainage, and the level-crossing works are to be carried out as a priority tranche. The ESIA also identifies the signalling system as needing modernisation.

Phase 2 will cover complementary works whose design and footprint are to be defined by technical studies, and SNCFT has committed to updating the ESIA once Phase 2 is approved.

Traffic and Timetable

SNCFT statistics in the ESIA record 60,953 passengers and 81,472 tonnes of freight on the line in 2025, with around one passenger train and one freight train a day. The project aims to provide a safer, faster and cleaner rail link between the Bizerte governorate and Greater Tunis and to ease the movement of freight such as cement and steel from Bizerte and Menzel Bourguiba to Tunis.

The ESIA puts the works phase at about 24 months, with the design and tender documents phase running until the end of the first quarter of 2027. Public consultations were held in eight sessions between 2 and 16 September 2026, and the environmental and social management plan carries a budget of 3,480,000 dinars (€1,044,000).