Archive | Gautrain Progress

GAUTRAIN PROGRESS: PRETORIA-HATFIELD

Posted on 19 February 2010 by Railways Africa Editor

VIADUCT 7 The deck to the section that will carry the Gautrain lines across Nelson Mandela Boulevard is well advanced and parapet erection is in progress. Pier and trestle beam construction continues on the remaining sections of this “Y-shaped” structure that crosses above the existing Metrorail tracks, together with placing of the M-beams for the bridge [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN PROGRESS: MIDRAND-CENTURION-PRETORIA

Posted on 19 February 2010 by Railways Africa Editor

VIADUCT 3 North of the depot, Viaduct 3 over Allandale Road and the adjacent bridge over the future K60 road are both complete, as are all other bridges, construction works and railway installations up to Dale Road in Midrand, with only minor finishing works outstanding. [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN PROGRESS: MARLBORO-DEPOT-MIDRAND

Posted on 19 February 2010 by Railways Africa Editor

Viaduct 2 over the Modderfontein Spruit and two adjacent bridges over the future Frankenwald and Maxwell Roads are complete, together with the erection of noise barriers along this section. Track and overhead electrification is in position on all three structures. Midrand Depot The administration buildings for both train and bus depots are finished and the installation of [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN PROGRESS: ROSEBANK-SANDTON-MARLBORO

Posted on 19 February 2010 by Railways Africa Editor

Emergency shafts E5 (Dunkeld, Rosebank), E6 (Illovo) and E7 (Rivonia Road, Sandton): Construction is in progress on the technical rooms at the bottom of these shafts, and also on the safe haven at the foot of Shaft E5. SANDTON STATION At 45 metres (15 storeys) below ground level, Sandton station is Gautrain’s deepest. Station construction work is well advanced [...] [...more]

Gautrain Progress Comments (1)

GAUTRAIN PROGRESS: PARK TO ROSEBANK

Posted on 19 February 2010 by Railways Africa Editor

PARK STATION The station roof and concourse slabs as well as the platforms are all substantially complete. Internal brickwork and plastering is well advanced at both concourse and platform levels. Good progress is being made with wall tiling, together with mechanical and electrical (M&E) installations. Three of the six levels of deck slabs have been cast [...] [...more]

Gautrain Progress Comments (1)

GAUTRAIN PROGRESS: MARLBORO-AIRPORT

Posted on 19 February 2010 by Railways Africa Editor

Civil construction work is complete along the whole of this section which includes eleven bridges, three viaducts and a number of other structures, including the platforms for a future station at Modderfontein. Remaining work is limited to final finishing and landscaping in some places. VIADUCTS 13 & 14 Viaduct 13 over Centenary Way in Modderfontein and Viaduct [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN “A BIG BLIP” ON M & R RESULTS?

Posted on 15 January 2010 by Railways Africa Editor

According to an observer on All Africa Global Media, the Murray and Roberts group (M&R) expected half-year bottom-line diluted headline earnings per share to be between 15% and 20% lower than in the comparable previous period. In August 2007, the private investor portfolio paid a gross share price of R71.04 for its holding in M&R. [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN PROGRESS: MIDRAND-CENTURION-PRETORIA

Posted on 24 December 2009 by Railways Africa Editor

VIADUCT 3 North of the depot, Viaduct 3 over Allandale Road and the adjacent bridge over the future K60 road are both complete, as are all other bridges, construction works and railway installations up to Dale Road in Midrand, with only minor finishing works outstanding. [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN PROGRESS: MARLBORO-DEPOT-MIDRAND

Posted on 06 December 2009 by Railways Africa Editor

Viaduct 2 over the Modderfontein Spruit and two adjacent bridges over the future Frankenwald and Maxwell Roads are complete, together with the erection of noise barriers along this section. Track is in position on all three structures. Midrand Depot The administration buildings for both train and bus depots are finished and the installation of equipment for the [...] [...more]

Gautrain Progress Comments (0)

GAUTRAIN PROGRESS: MIDRAND-CENTURION-PRETORIA

Posted on 06 December 2009 by Railways Africa Editor

VIADUCT 3 North of the depot, Viaduct 3 over Allandale Road and the adjacent bridge over the future K60 road are both complete, as are all other bridges, construction works and railway installations up to Dale Road in Midrand, with only minor finishing works outstanding. MIDRAND STATION At Midrand, station building works, including the structural steel roof structures [...] [...more]

Gautrain Progress Comments (1)