GAUTRAIN TRACKLAYING PROGRESS
Posted on 20 July 2009
Gautrain’s route requires 150km of track in all. By the end of June, 37km had been installed – about 24% of the total. Track construction inside the tunnels is utilising a “state-of-the-art” system, consisting of pre-cast concrete blocks surrounded with a rubber boot cast into concrete. Sections of track outside the tunnel are using conventional ballasted track.